Street Project Updates

As the 2020 Street Projects begin, we will keep you updated on what you need to know! Here is some basic information.

Work continues on Stage 7 of the IA13 project. Work will continue with concrete grading and possibly milling next week with HMA the last week of July. Pirc Tobin will likely begin sidewalks and storm sewer in Stage 5 late next week or the last week of July. The current detour will remain in place for the next few weeks with work in stage 7 expected to be wrapping up the first part of August.