As the 2020 Street Projects begin, we will keep you updated on what you need to know! Here is some basic information.

Working is progressing well on the IA 13 project with a lot of concrete being placed this week with River Street to reopen prior to this Saturday‚Äôs Farmers Market.  Next week we anticipate seeing West Main Street from the bridge to Franklin Street being milled and surfaced with HMA and work beginning at the intersection of N Franklin and Seeley Street.  Following is the contractors proposed schedule which is subject to weather.

Monday (Memorial Day)

No work.

Tuesday

Set up traffic control to close Stage 6 (Seeley Street intersection) on Wednesday morning.

Tuesday or Wednesday

Seeding to be completed on River Street and Stage 1 (west of bridge).

Wednesday

Close Stage 6 (Seeley St Intersection) and mill existing HMA on Stage 3 (W Main Street) and Stage 6 (Seeley St intersection).

Thursday/Friday

Stage 3 (W Main Street) HMA paving. Plan to have W. Main paved by the end of the month. Pavement markings may be the first part of the following week.

Stage 6 (Seeley Street Intersection) is prosed to begin on Wednesday May 27th and will take 3 to 4 weeks. The section of North Franklin to be closed is from houses 940/941 on the south end through houses 1012/1009 on the north end. Following asphalt milling on Wednesday work will proceed to removals, fire hydrant relocate, storm sewer and then new curb, drives & sidewalks and paving.  From Stage 6 work will proceed directly into Stage 7 (Acers Street intersection) which will take about 6 weeks.

The primary detour of IA 13 using IA3, IA 38 and US 20 will remain in place through stages 6 and 7.  Local detour for Stage 6 is as follows and shown on the attached image.

South bound traffic will head east on Acers, south on New and then west on Clara back to Franklin. No parking will be posted along the entire route.

North bound traffic will east on Prospect, north on Sherman and then west on Acers back to Franklin. No parking will be posted along the entire route.